Capacity Expansion Planner

New capacity ?
–
Present cost ?
–
LCOE ?
–
Clean energy
–

Capacity and when to build

Hover a year to read what is in service, and what its decision year builds and retires.

Energy by source

Hover a year to read where its energy comes from.

Typical days

Hover an hour to read the dispatch.

Cost by year

Hover a year to read its costs.

Results by year

What this assumes

    Questions

    How is a whole year of demand represented in the plan?

    Each decision year is run hour by hour over typical days of each season, and every hour is weighted by the hours of the year it stands for. A temperate climate has four seasons and a tropical one two. With One typical day, each season is a single weekday. With the 'A weekday and a weekend day' or 'A typical week' choices it is finer, but slower to solve.

    How does the plan count the capital cost of a new plant?

    Capital is paid as an annuity of the overnight cost at the Discount rate (7% real by default) over the plant's life, only for years inside the plan. At 7% a 25-year life costs about 8.6% of the overnight cost a year. The first payment falls in the year it enters service, so a plant that lives out its life inside the plan pays 1.07 times its overnight cost.

    Does the plan include transmission, reserve margin or start-up costs?

    No. The grid is a single copper-plate bus: every plant serves every load with no network limits or losses, and every hour is known in advance. Firm plants run anywhere from zero to their availability, with no start-up costs or minimum output, and no reserve margin is held beyond what the typical days need. To allow for it, lower a plant's Availability or turn on the still, overcast peak day.

    What does the still, overcast peak day add to the plan?

    It adds one extra day in the peak season with a quarter of the normal sun and a tenth of the normal wind, standing for 2 days of that season each year. The plan then has to serve peak demand with almost no solar or wind, so it holds more firm capacity or storage. Without it, a plan can lean on solar and wind that the typical days always deliver.

    What is the difference between a real and a nominal discount rate here?

    All money is at first-year prices, so the plan always runs on a real rate. Real mode takes the Discount rate as typed. Nominal mode converts it as (1 + nominal) divided by (1 + inflation) minus 1, so 10.2% nominal with 3% inflation is about 7% real. At 7%, a cost ten years out counts about 0.51 of the same cost in the first year.

    Why does a plant that retires partway through a decision step keep running?

    A decision year counts in whole. A plant in service in it runs, and is paid for, in every year that decision year stands for, which is up to 5 years with the default Years between decisions. So a retirement date or a life ending mid-step runs on to the end of the step. Choosing 1 year between decisions removes this, at the cost of a bigger problem to solve.